Increased firefighting capability for Roma - New water mains to be installed

The first water main will be installed on Lewis Street South (from Conlan Street) and along Newbon Street, with the second main to be installed on Tiffin Street (between Chrystal Street and Bowen Street).

The works will commence on Monday, 12 August and are anticipated to take eight weeks to complete (weather permitting).

Traffic management will be in place for the safety of both the workers and road users. Council asks that you please follow the direction of traffic controllers and signs during this period.

For more information, please contact Council's Water Team on 1300 007 662. 

<