Line marking to commence in the Maranoa this week

Maranoa Regional Council wishes to advise Maranoa residents that the Line Marking Program will be undertaken over the next three weeks (weather permitting) starting this week.

Works are scheduled between 6am and 6pm and includes a refresh of existing faded lines.

Council will coordinate works to minimise disruption to residents and traffic management will be in place to assist motorists while line marking works are underway.

Line marking delivery program:

Week 1:

  • Yuleba
  • Wallumbilla
  • Surat

Week 2:

  • Mitchell
  • Mungallala

Week 3:

  • Injune

For more information, please contact Council’s Maintenance Delivery and Works Team on 1300 007 662.